When is an application for site plan review considered complete?

Prepare for the New Jersey Professional Planner Exam with detailed quizzes and flashcards. Understand complex concepts through multiple-choice questions, complete with hints and explanations, to excel in your exam!

An application for site plan review is considered complete when 45 days have passed without certification. This rule helps to ensure that applications are processed in a timely manner and that there is an accountability mechanism for municipal boards. According to New Jersey's Municipal Land Use Law, if the reviewing authority does not certify the application as complete within that timeframe, it is automatically deemed complete. This provision is essential for applicants because it prevents undue delays in the review process, allowing them to move forward with their projects without being held up indefinitely.

The options mentioned provide different aspects of the review process, but the 45-day timeframe establishes a clear standard for determining completeness. Thus, the focus on this particular period underscores the importance of efficiency in municipal planning and the right of applicants to receive timely evaluations of their proposals.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy