What is the minimum required time a planning board has after receiving a complete application to act on a preliminary subdivision application for fewer than 10 lots?

Prepare for the New Jersey Professional Planner Exam with detailed quizzes and flashcards. Understand complex concepts through multiple-choice questions, complete with hints and explanations, to excel in your exam!

The minimum required time for a planning board to act on a preliminary subdivision application for fewer than 10 lots is 45 days. This timeframe is established under New Jersey’s Municipal Land Use Law, which aims to ensure that applications are processed in a timely manner, thus providing a clear expectation for both applicants and the planning boards.

The 45-day period allows the planning board to review the application fully, consider any necessary modifications, and respond adequately to any concerns raised during the review process. This period is particularly important for smaller subdivisions, as it promotes efficiency while still allowing for adequate public input and consideration of regulatory requirements.

In contrast to the other timeframes mentioned, such as 30, 60, or 90 days, the 45-day requirement strikes a balance between promptness and thoroughness in the review process, making it an essential guideline for managing local development responsibly. This timeframe reflects an understanding of the need for local government to be responsive while still fulfilling its role in land use planning.