What is the maximum time allowed for a planning board to approve a general development plan after receiving a complete application?

Prepare for the New Jersey Professional Planner Exam with detailed quizzes and flashcards. Understand complex concepts through multiple-choice questions, complete with hints and explanations, to excel in your exam!

The maximum time allowed for a planning board to approve a general development plan after receiving a complete application is 95 days. This timeframe is established to ensure that applicants receive a timely response to their proposals while also allowing planning boards to thoroughly review the applications. The 95-day period reflects a balance between efficiency and due diligence in the planning review process.

By setting a specific deadline, the law encourages planning boards to be organized and prompt in handling applications, which can often involve complex considerations related to zoning, land use, and community impact. It also provides applicants with a clear expectation regarding the timeline for the decision-making process, which can aid in their planning and investment strategies.

The other time frames provided do not align with the statutory requirements for New Jersey planning boards, making them unsuitable as valid responses to this question.