For how long does a planning board have to act on a preliminary subdivision application that involves 10 lots or fewer?

Prepare for the New Jersey Professional Planner Exam with detailed quizzes and flashcards. Understand complex concepts through multiple-choice questions, complete with hints and explanations, to excel in your exam!

The correct duration for a planning board to act on a preliminary subdivision application involving 10 lots or fewer is 45 days. This timeframe is established to ensure timely consideration of subdivision applications, allowing developers to receive timely feedback and for the planning board to manage its workload effectively.

In New Jersey, the statute specifies that the planning board's decision must be made within this 45-day period from the date of the application being deemed complete. This requirement is in place to facilitate efficient governance and ensure that development proposals are reviewed and acted upon in a timely manner, which is vital for maintaining economic development and community planning processes.

Understanding this timeline is important for both planners and developers, as it helps in setting expectations for the development review process and aids in project scheduling.